S.2359 sponsored by Senator Brendan Crighton and H.3753 sponsored by Representative Steven Owens and Representative Jennifer Armini
The bill orders the MBTA to fully electrify the entire commuter rail system by the end of 2035. It also specifies that there must be a short-term plan to immediately electrify the Fairmount line, the Providence/Stoughton line, and part of the Newburyport and Rockport lines by the end of 2029, and that must give priority consideration to lines serving environmental justice populations.
“The plan shall include, but not be limited to: (i) a detailed critical path schedule for each phase; (ii) cash flow needs organized by fiscal year through completion of each phase; (iii) a regional strategy to receive all necessary environmental approvals and permits; (iv) identification of needs from utilities to achieve adequate and redundant power to update the system; (v) a platform strategy that would enable the utilization of fully automated doors; (vi)target completion dates; (vii) a conceptual work plan; and (viii) a schedule outlining the work to be pursued over the course of the Fiscal Year 2025-2029 Capital Plan.”